June 1, 2022
Pavement Work Progresses – Timelapse Video
Since airside paving operations started on the New Terminal at Kansas City International Airport in August 2021, crews have poured nearly 45 percent of the more than 450,000 square yards of pavement that will create the New Terminal’s aircraft parking aprons and taxiways. On average, crews are able to pour approximately 2,000 cubic yards of concrete per workday. Paving will continue throughout 2022. Watch the timelapse video.