/

Parking Garage Work Progresses

May 2021 B-roll video of the Kansas City International Airport New Terminal shows how far along the parking garage has come under JE Dunn Construction and Edgemoor. View the video.

Read More

/

Glass Panels Added to Garage Mock-Up

As work progresses on-site at the Kansas City International Airport New Terminal’s parking garage, the garage mock-up continues to evolve off-site. Glass panels were recently placed on the mock-up to verify color samples, connections, assembly...

Read More

/

Bricklayers Working on Tug Road

At nearly 600 feet long and 20 feet high, the Kansas City International Airport New Terminal’s tug road is nearing completion. Bricklayers have been hard at work for several months creating the tug road walls...

Read More

/

Cooling Towers Installed

Massive cooling towers were recently installed above the KCI Airport New Terminal’s Central Utility Plant. Crews continue pipework installation around the cooling towers ahead of the early June milestone of blowing cool air in the...

Read More

/

Work Progresses on Parking Garage (Video)

The KCI Airport New Terminal parking garage is 35 percent complete with over 1,500 precast concrete panels in place. When complete in 2022, the garage will be 70 feet high and have more than 6,000...

Read More

/

First Escalator Installed

The first escalator on the Kansas City International Airport New Terminal Project is in place! When arriving at KCI’s New Terminal on an international flight, this escalator will take customers from the second level to...

Read More

/

Installation of Baggage Handling System Continues

Work continues on the new baggage handling system as crews from Vanderlande install belts and conveyers on the arrivals level of the Kansas City International Airport New Terminal. When complete, there will be more than...

Read More