New Terminal Steel Progress Time Lapse Video

Erector set Build KCI-style! The Build KCI team began installing the first vertical steel beams of the New Terminal at Kansas City International Airport on Monday, April 6, 2020. As of June 9, 2020, 1,490 pieces of steel have been erected and 125,297 square feet of metal deck have been installed. Check out the time lapse video shot from the 256-foot FAA Air Traffic Control Tower! Work starts in the background on left and later simultaneous work begins in the right foreground.