Garage Now Twenty Percent Complete

The Kansas City International Airport New Terminal parking garage is just over 20 percent complete with more than 975 precast pieces in place. At a weight of approximately 40,000 pounds, each concrete piece comes in at more than 60 feet long. On average, crews are able to install 20 panels each day. Click on the photos below to enlarge.