Concrete Deck Pours Continue

The first concrete deck pour on the KCI New Terminal Project’s elevated roadway is complete. Crews started at 3:00 AM last Friday morning to coordinate the arrival of more than 25 cement trucks to pour the first 250 cubic yards of the roadway’s surface.