June 4, 2021
Garage Tower Glass Installation
Nearly 75 percent of the glass is in place on the Kansas City International Airport New Terminal parking garage’s south elevator and stair tower with additional glass installations scheduled for the north tower later this month. When complete, there will be more than 125 individual pieces of glass on the elevator and stair towers. To date, a little more than 50 percent of the parking garage precast panels have been installed. The garage is scheduled for completion in early 2022.