Garage Precast Concrete Work Began This Week

The Build KCI team heads into the Thanksgiving weekend having hit another project milestone on the Kansas City International Airport New Terminal project: the start of parking garage precast concrete. Crews placed the first of more than 4,400 pieces of precast concrete with the installation of six 35-foot beams. The garage, when complete, will reach 70 feet in height and provide more than 6,000 parking spaces for the traveling public. View the video.